Building in the city centre of Warsaw with striking concrete and glass façade 

Height: 70 m

Storeys: 19

Shell construction period: 11 months

Construction period until opening: 2007 – 2011

 

 

Location
Main Application
Buildings
Project participants
Customer: Warbud S.A., Warsaw

The Project

Impressions from the project process

Project Information

Prosta Tower - Rafał Rusek, Project leader
Prosta Tower - Rafał Rusek, Project leader
Rafał Rusek
Project leader
This project was a great challenge for us because fair-faced concrete jobsites often mean a lot of risks. However, with PERI we have found a proficient and experienced partner. This enabled us to safely and successfully implement the project due to PERI’s perfect logistics and prefabricated formwork.
Interested in learning how PERI can support your next project?

Call us on +971 (0) 4 326 2992 to discuss your requirements further.

Location

Prosta Tower, Poland

Prosta Tower, Warsaw, Poland - The PERI UP scaffolding extended upwards on the outside keeping pace with the construction progress.
Prosta Tower, Warsaw, Poland - The PERI UP scaffolding extended upwards on the outside keeping pace with the construction progress.