21st Century Tower, United Arab Emirates
Dubai

  • overall height: 269 m
  • construction period: 2001-2003
  • stages: 55


Joint Venture Arabtec Construction and Al Rostamani Pegel

Location
  • Benefits
    short construction time in 3-day cycle for one storey with an area of 1,350 m²
  • Benefits
    considerable amount of crane capacity saved thanks to ACS self-climbing technology

The Project

Impressions from the project process

Project Information

PERI ACS is unbelievably quick and extremely safe. We were able to save a considerable amount of crane capacity thanks to the self-climbing technology. That is a huge advantage on construction sites like these.
P. Schneider and G. C. Christofides
Site Manager | Project Manager